Project

Project

Location

In April 2019, TCC began discussions with the City of Toronto and CreateTO, the City’s real estate agency, to identify a suitable site for the project. In October 2020, Toronto City Council voted unanimously in support of 311 Staines Road as the future site of the TCC. At 16,722 square metres or 4.13 acres, the land is valued at approximately $25 million. The land is centrally located in relation to the highest concentration of Tamil residents in the GTA. A land lease was finalized between the City and TCC in 2021 with annual rent of $1 dollar plus HST.
4.11
acres of land at 311 Staines Road

Funding

In July 2021, the Government of Canada and the Government of Ontario announced $26.3 million in funding for the construction of the Tamil Community Centre through the Investing in Canada Infrastructure Program. The remaining costs of construction will be fundraised by the Tamil community. 
$ 26.3 M
in government funding
Proposed Site Plan (subject to fundraising achievement).
Proposed Site Plan (subject to fundraising achievement).
Proposed Floor Plan - First Floor (subject to fundraising achievement).
Proposed Floor Plan - First Floor (subject to fundraising achievement).
Proposed Floor Plan - Second Floor (subject to fundraising achievement).
Proposed Floor Plan - Second Floor (subject to fundraising achievement).

Next Steps and Milestones

Next Steps

February  - June 2024
1

February - June 2024

Feasibility & Design
Take drawings from Pre-Design to Schematics ready
March - June 2024
2

March - June 2024

Engagement
Re-engage 150 organizations and collect feedback on program spaces Engage Broader Tamil community
August - October 2024
3

August - October 2024

Finalize Design and Site Plan
Engage all consultants and prepare drawings for submission to city ZBA, SPA
October 2024 - September 2025
4

October 2024 - September 2025

Planning Approvals
City reviews and approves ZBA/SPA
January - June 2025
5

January - June 2025

Tendering Process
Draft release, and secure contractor through RFP process
October 2025 - August 2027
6

October 2025 - August 2027

Construction
Site construction begins in October 2025 and ends in August 2027
cta image